Design & Installation of tetra Pak Chimney

Design & Installation of Tetra Pak Chimney

During the design of chimney, main problem occur was the space allotted for the placement of chimney & type of chimney design (Conical Self Supported Chimney), also there was some minor problem like orientation of chimney, access to top of chimney, etc.
To overcome the challenges we came up with different design standards like MPCB, OSHA 3124 , IS6533-1 ,IS6533-2 . After complete study we came o conclusion that we cannot design he chimney with any one standard, so we merge some part of each standard & design the Self Supported chimney. Some of the changes made were

For his whole process it took 7 weeks of hard work for approval of design & the end result was mesmerising to see, at last hard work payoff.

Cummins India Ltd

Cummins India is one of the reputed company for DG set manufacturing .The whole project was basically unloading , & installation of 4 Compressors & six 5cu mtr Receiver with its accessories & Electrical panel installation along with 4 soft starter panel . The main problem while working in plant was that we have to do install the compressor in basement and receiver on first floor. Following activity were done to over come problems.

For his whole process it took 3 weeks of hard work for approval of HIRA document , gate pass & installation the end result was mesmerising to see, at last hard work payoff.

Cummins India Ltd
Goa Shipyard Project

Goa Shipyard Project

During the initial stages of Project he main problem was that the gate pass was to be made from CISF security & they were taking test for each welder. We didn’t know the site condition because we haven went to site before. The whole project was basically unloading & insallaion of 110KW Compressors, two 5 cu mtr Receivers, 1 desiccant dryer , 1 refergerent dryer with its accessories& Plant piping. Following activity were done to over come problems.

For his whole process it took 4 weeks of hard work for approval of HIRA documents , gate pass & installation the end result was mesmerising to see, at last hard work payoff.

KSPG Ahmednagar Plant Dismantling work

KSPG automotive plant was basically Kirlosker Ball bearing plant .The whole project was basically dismantling of whole plant which include Machine , LT cable , chimney, Furnace ,etc. The main problem while working in plant was that we have to do maximum work without crane as there was less space available and within target time of 40 Days & problem in LT panel cable removal. Following activity were done to over come problems.

KSPG Nagar Plant Dismantling work
Par Formulation Indore Project

Par Formulation Indore Project

During the initial stages of Project he main problem was that the customers office was in Mumbai & the installation was to be done in Indore. We didn’t know the site condition because we haven went to site before. The whole project was basically supply of Air receiver , unloading , & insallaion of Compressors with its accessories. Following activity were done to over come problems.

For his whole process it took 6 weeks of hard work for approval of design & installation the end result was mesmerising to see. We get Repeat order for Same Compressor package installation.